10K
AdministratorAdministrator
10K

PostDec 13, 2006#176

The Central Scrutinizer wrote:They've been pounding away with a jackhammer the past few days. Looks like they are removing the old entrance?


From the renderings, it looks like the part of the facade they're working on will be all glass. I can't wait to see how it turns out!

48
New MemberNew Member
48

PostDec 15, 2006#177

Walked by the Dorsa this afternoon. Looks like they're pretty much done reshaping the entrance of 1007. I'm sure once they get the glass in it will look awesome.



Also, on the back of 1013 (15?), it looks like they've cut into the brick under one of the windows (out of the set of 3) in order to create the doors for the balconies. This is of particular interest to me because that includes my unit ;)



Also, I know JimJim in convinced the contracts are coming out. Certainly signs seem to point to this; I got a reply from on Wed. saying they were having a meeting on the Dorsa tomorrow (yesterday). What exactly was determined at this meeting, I don't know. I hope that we do get them next week so we can get the ball rolling.

173
Junior MemberJunior Member
173

PostDec 16, 2006#178

The meeting was with the development staff to "shove off contracts."

48
New MemberNew Member
48

PostDec 27, 2006#179

If that is the case...they didn't happen to say when we would get them? Or has anyone gotten theirs already?

1,137
Expert MemberExpert Member
1,137

PostDec 27, 2006#180

JimJim15 wrote:The meeting was with the development staff to "shove off contracts."


What does that term mean?

5,631
Life MemberLife Member
5,631

PostDec 27, 2006#181

bsharmastl wrote:
JimJim15 wrote:The meeting was with the development staff to "shove off contracts."


What does that term mean?
What do they mean by "contracting?" Actual mortgage payment from bank to developer? When are people tentatively scheduled to begin moving in? Bring on more people to downtown!

1,137
Expert MemberExpert Member
1,137

PostDec 27, 2006#182

What does the term "<b>shove off</b> contracts" mean.

Man.... You are innovative :)

5,631
Life MemberLife Member
5,631

PostDec 28, 2006#183

bsharmastl wrote:What does the term "<b>shove off</b> contracts" mean.

Man.... You are innovative :)
Heh, whatever it is they're delaying it I guess. I signed a contract when I reserved. Then I signed a mortgage contract when I closed... So yeah, they're not too specific.

1,137
Expert MemberExpert Member
1,137

PostDec 28, 2006#184

Oh... so they meant the dates. OK. That makes sense.

48
New MemberNew Member
48

PostJan 17, 2007#185

Finally...the wait is over, this milestone is reached...



CONTRACTS!!!



I got mine last night, though unfortunately, I didn't have the time to give it a thorough perusing.



I'm just happy it's here.

10K
AdministratorAdministrator
10K

PostJan 17, 2007#186

^

Does this mean you'll be moving in soon, or is that still a ways off?

173
Junior MemberJunior Member
173

PostJan 17, 2007#187

DeBaliviere wrote:^

Does this mean you'll be moving in soon, or is that still a ways off?


Nope. It's a ways off. Here's how it works in Dorsa:



When you decide you want a place (for many of us it was over a year ago), you sign a reservation and pay $2500. This reserves the unit you want until it's time to go to contract.



Now, we're at the "going to contract" stage. This is where we pay another $2500 and sign the actual contract that makes us responsible for buying the loft(s) when they're done. After we go to contract, we select upgrades which are added to the contract.



At that point, we will have paid $5000 (which goes toward the cost of the loft) plus a certain percentage of the upgrades we've selected. We'll then wait until June-July for the first of the units to be completed, at which point we'll start closing on the lofts (which is when we actually pay and move in).



So at this point, those of us who've paid to reserve a loft will be legally contracting to buy the loft at some point in the future. Up until the time we go to contract, we're allowed to back out and get the initial $2500 reservation fee refunded. After we go to contract, the $2500 reservation fee and the $2500 contracting fee are non-refundible.



So basically, it's just another stage in the process that is primarily designed to weed out speculators (who've become a little jumpy about the process) and those who aren't series enough to possibly lose $5000 if they decide they don't want the loft in the future. It's a good thing to do before you start allowing people to choose upgrades ... if you let people pick upgrades before they were bound by non-refundable money, you'd risk personalizing lofts for people who may not take them in the end.

PostJan 18, 2007#188

I just got my contract packet as well, and I have a question for any Dorsa buyers out there ...



In my upgrades list, I have a page that lists Groups 1-6 for Tub and Shower Surrounds. The page before it lists Groups 1-4 for Bathroom Floors and the page after it lists the prices (per floorplan) of the Bathroom Floor Groups.



However, I can't find anywhere in my upgrades packet a list for the prices per floorplan for the Groups 1-6 of the Tub and Shower Surrounds that are listed. But there was an option earlier in the upgrades packet that priced having cultured granite as a Tub and Shower Surround. Am I missing something?

PostFeb 01, 2007#189

So, has anyone signed and returned their contract yet? I saw a few lofts are listed on the Dorsa website as having gone to contract, and I'm wondering if anyone who reads this board is among them ...



At this moment, these are the units listed as having gone to contract:



304 (Me and my mife)

305

308

409

and 2 penthouses.



That's 6 in total, with upgrades selection to go by floor starting in mid-February. I'm excited.

48
New MemberNew Member
48

PostFeb 01, 2007#190

My wife and I are in 308. So I guess for the third floor selections would be late Feb/early March, by that reckoning.

144
Junior MemberJunior Member
144

PostFeb 01, 2007#191

Does anybody know what the street crews are doing in front of the Dorsa? Half of the street is now under construction and there is massive piece of something sitting on the side of the street. I was wondering if they've encountered some structural issues underground or if there was simply a water main break from the cold. If anybody can shed some light on this, that'd be great.

173
Junior MemberJunior Member
173

PostFeb 06, 2007#192

New progess pictures up at the Dorsa website.



http://www.dorsalofts.com/progress.php



These are November, December, and January pictures ... looking at some of the first ones, it looks like not so much has been done, but looking at the later ones, the elevator shaft is looking good, some walls are being framed, and electric, gas, and plumbing lines are looking good.



Also, I think another unit has gone to contract.



And to answer the question in the post above, the pictures show the facade refinishing about to start ... so that's probably why the street is partially blocked. There's a lot of work to be done of the front of Dorsa, but man it's going to look good.

5,631
Life MemberLife Member
5,631

PostFeb 06, 2007#193

The Dorsa has such a beautiful, unique facade and the area is fantastic. Looking forward to seeing it completed and people moved in... Does anyone know the tentative schedule for completion of the first units? 6, 9, 12 months?

173
Junior MemberJunior Member
173

PostFeb 06, 2007#194

Dorsa is scheduled for 2nd floor closings in June-July, with 3rd floor to be July-August, and subsequent floors to follow every 2-4 weeks.

6,775
Life MemberLife Member
6,775

PostFeb 06, 2007#195

JimJim15 wrote:Dorsa is scheduled for 2nd floor closings in June-July, with 3rd floor to be July-August, and subsequent floors to follow every 2-4 weeks.


Which probably means:



2nd floor closings in Oct-Nov, with 3rd floor to be Dec-Jan08, and subsequent floors to follow every 6-8 weeks.

48
New MemberNew Member
48

PostFeb 06, 2007#196

The Central Scrutinizer wrote:
JimJim15 wrote:Dorsa is scheduled for 2nd floor closings in June-July, with 3rd floor to be July-August, and subsequent floors to follow every 2-4 weeks.


Which probably means:



2nd floor closings in Oct-Nov, with 3rd floor to be Dec-Jan08, and subsequent floors to follow every 6-8 weeks.


I contest that. As far as finishing and closing schedules are concerned, Pyramid has a pretty good track record after contracts are out. Banker's closings were a month behind only because of certain material difficulties (the elevators, if I remember correctly), and the aforementioned 2-4 weeks per floor was about right on.

173
Junior MemberJunior Member
173

PostFeb 06, 2007#197

StLRisen wrote:
The Central Scrutinizer wrote:
JimJim15 wrote:Dorsa is scheduled for 2nd floor closings in June-July, with 3rd floor to be July-August, and subsequent floors to follow every 2-4 weeks.


Which probably means:



2nd floor closings in Oct-Nov, with 3rd floor to be Dec-Jan08, and subsequent floors to follow every 6-8 weeks.


I contest that. As far as finishing and closing schedules are concerned, Pyramid has a pretty good track record after contracts are out. Banker's closings were a month behind only because of certain material difficulties (the elevators, if I remember correctly), and the aforementioned 2-4 weeks per floor was about right on.


I agree. Pyramid has WAY too many big projects after Dorsa to drag this one out ... Arcade-Wright, and City Center being two of the biggest. They don't want to dilly dally.



And yeah, they were spot on with Bankers. Plus, in talking to them, they say things like, "I can't guarantee anything, but we've been doing this a long time, and from my experience, things are right on track." Hearing that from someone you trust makes you feel at ease.



Not that something couldn't come up, but right now we're doing well.

729
Senior MemberSenior Member
729

PostFeb 06, 2007#198

I look forward to this building being done. It will really help finish off that stretch of Wash. Ave. That little block is quickly becoming a very active spot. And finally being able to park cars on the streets down there really helps in my opnion. I originally had unit 304 under reserve but backed out. Would love to get in there once completed to see how it turns out!

8,912
Life MemberLife Member
8,912

PostFeb 06, 2007#199

we hear what's going in the frist floor yet?

173
Junior MemberJunior Member
173

PostFeb 06, 2007#200

irocktheparty2000 wrote:I look forward to this building being done. It will really help finish off that stretch of Wash. Ave. That little block is quickly becoming a very active spot. And finally being able to park cars on the streets down there really helps in my opnion. I originally had unit 304 under reserve but backed out. Would love to get in there once completed to see how it turns out!


Gosh. How long ago did you have 304 reserved? We've had it for 15 or 16 months now, and I don't remember it being reserved before that (at least, while I was paying attention). But then, I'm sure the Dorsa project had legs before my wife and I found it.



As far as the first floor, they're being very quiet about it. I wouldn't be surprised if they wanted to keep it secret so that whoever it is can make a big announcement about it or something. But they're sure working on it pretty hard. Originally, I heard it might be something like a Whole Foods or some such store, but now I hear a Trader Joe's is going in down the street, so I doubt we're getting the grocery. I've also heard it might be a Pin-Up Bowl, which might be kinda fun.

Read more posts (223 remaining)