8,155
Life MemberLife Member
8,155

PostJun 05, 2014#126

Nothing earth-shattering, but another vacant lot on Washington west of Vandeventer will be filled in... a $1.5 million permit has been issued for an assisted-living facility at 3950 Washington.

12K
Life MemberLife Member
12K

PostJun 05, 2014#127

Hmmm...I've been wondering what they were clearing the ground for at that site. Sounds like its gonna be quite small; probably associated with one of the nearby churches.

1,093
Expert MemberExpert Member
1,093

PostJun 05, 2014#128

I didn't see the Municipal Courts building on the list. Is it dead?

8,155
Life MemberLife Member
8,155

PostJun 05, 2014#129

^ I believe so for now. I can add it to the Keep an Eye on though.

edit: its being actively marketed now.

PostJun 16, 2014#130

I noticed cranes are up now at the STLCOP and Citywalk sites.... I enjoyed the view on Euclid of the Citywalk crane in foreground and the McKinley Research and STLCOP cranes in the background. More should be coming soon!

PostJul 01, 2014#131

Big slowdown in project completions and starts in the second quarter compared to the first quarter.

Some nice milestones on key projects such as the Arcade-Wright and IKEA but few openings and only a few detailed plans for new projects.... I'd say the highlight on that front would be for the UIC mixed-use proposal.

Some upcoming openings in the coming weeks though should include the Magnolia Hotel downtown, new Police HQ in downtown west and the South Grand Rooster in the old Commerce Bank. Hopefully we'll have a fair number of the "Keep an Eye Ons" get moved over to firmer ground.

933
Super MemberSuper Member
933

PostJul 01, 2014#132

It's gonna be 2017 or 2018 before we're seeing loads of openings and major new construction on a regular basis, but when that time comes we'll look back on today and think "Hah, that was cute. Remember when we were still waiting for the Arcade to get going? And when there weren't any new high-rises under construction yet at all? Jeeze...What was St. Louis' deal back then?"

8,155
Life MemberLife Member
8,155

PostJul 01, 2014#133

True the coming years should see an accelerated pace but I'm hopeful some of these will being currently bandied about actually move forward this year.

Also forgot to mention that construction should start within the next month or so on the Loop Trolley, National Blues Museum and Arcade-Wright, so that will keep some of the excitement going.

284
Full MemberFull Member
284

PostJul 01, 2014#134

Things are starting to heat up! I would love to see the Chemical actually come to fruition its been put on the back burner forever also love to the Jefferson Arms come to life sooner than later that will definitely inject some new life on Tucker & Wash Ave. In all i think we're in store for some very exciting times here the heck I'm very Hyped about the IKEA breaking ground & now the Loop Trolley this area will definitely so a big transformation. My only request is the city should focus on an extensive city beautification ordinance the trash thats flying all over on our roads are a hazard & seeing old un used buildings alone make the city look dim so i wouldn't mind see a lot of things cleaned up on the roads side walks etc other than that I'm very excited/happy with the way things are progressing here..

8,155
Life MemberLife Member
8,155

PostJul 18, 2014#135

It's been some time, but finally movement on a bigger ticket item as the new Olive Street SLMPD HQ is dedicated tomorrow... actually the march over from Clark Street in the morning might be a pretty cool thing to see.

Magnolia Hotel and I-64/TG/Boyle may open by the end of the month as well. (Not sure if Sarah will re-open at the same time or if more work needs to be done there. I also dropped the Crescent Building at Cortex and Northside Regeneration Jefferson/Cass infrastructure work off the list as these may be pushed back into 2015.

edit: And ribbon-cutting for North Sarah Phase II was today!

91
New MemberNew Member
91

PostJul 19, 2014#136

I walk to day from Cherokee st. all the way to Soulard zig-zag through Benton park neighborhood all I can say is positive change is the air. Saw a bunch of rehabbing along the way.

8,155
Life MemberLife Member
8,155

PostJul 19, 2014#137

Completed Projects

Downtown
Gallery 515 apartments - 515 Olive (102 units; Millennium Center 11 floor apartment conversion)
Lacassian Lofts -- rehab of 2200 Locust (27 units + ground floor commercial)
CitiParc at Pine - 1531 Pine (149 senior housing units; was vacant Plaza Square Building)
Tower OPOP - 411 N. 8th (128 units + ground floor restaurant)
Stan Span and N. Tucker
t-rex move - rehab of occupied Lammert Building- 911 Washington
Ball Park Village Phase One
1010 Locust commercial rehab (old Bride's House Building)
U-Haul retail and storage facility occupying vacant "Globe Drug" Buildings - 418 S. Tucker
Union Station Grand Hall & Hotel rehab (Phase One of larger project)
New Police HQ -1915 Olive (conversion of old AG Edwards building)
Magnolia Hotel - 421 N. 8th

Central Corridor
Cortona @ Forest Park - 5800 Highlands Plaza Dr. (278 units)
Lacledes Lofts - rehab of 3965 Laclede (50 units)
Aventura at Forest Park Phase II - 4431 Chouteau (50 units)
Tower Grove Mews- Tower Grove & McRee (10 apartments + office and retail; partially open)
Lofts at WashU
4011 Delmar (Renovation into Residential for Veterans) (68 units)
New I-64 bridges/Tower Grove Interchange
@4240 - Cortex (conversion of 4240 Duncan warehouse)
908 Lafayette rehab for Mission Taco Joint
Fields Foods - 1500 Lafayette
St. John's UMC conversion into Link Auction Galleries - 5000 N. Washington (at Kingshighway)
Manchester Avenue Building Rehabs: 4191 for The Demo, 4195 for The Ready Room, 4465 for UCBC Grove Brewery
Sun Theater rehab for Grand Arts Academy- 3627 Grandel Square
3713-3719 installation of PXSTL public art installation (vacant lot)
Public Media Commons (adjacent to KWMU & Nine Network on Olive)
Jazz Saint Louis expansion - 3540 Washington
5231 Manchester rehab for Modern Brewing
Mercedes-Benz of Saint Louis - 5915 Berthold
Saint Louis Zoo South Campus clearance of FP Hospital and temporary landscaping

South City
2612 Wyoming (former Garfield School) rehab for supportive housing (25 apartments)
Cherokee Street Buildings Rehabs: 2701for Luminary, 2709 for Los Punk, 2728 for Yaqui's, 2732 for Art Bar, 2846 for Master Pieza's Pizza, 3409 Iowa for Kismet Creative Center
3128 Morgan Ford rehab for London Tea Room (Hyde Park Beer Building)
2800 Shenandoah rehab for Purple Martin bar/restaurant
4330 S. Broadway rehab for Universal Foods (formerly vacant big box grocery)
2232 Thurman rehab for The Station Gourmet Market and Event Space (Art Deco gas station)
5105 Columbia rehab for Park Avenue Coffee (retail and office/roasting center)
1704 S. Broadway rehab for R-Space and Café (art gallery & coffee shop)
1831 S. 7th - Subway/mixed-use building (2nd floor residential; previously vacant lot)
3457 Magnolia rehab for Tick Tock Tavern & Steve's Hot Dogs
2199 California - Lona's Lil Eats
4601 Morgan Ford rehab for MRCKA Dojo Pizza (conversion of vacant church)
Peter Mathews Memorial Skate Garden -- 4415 Morgan Ford (former vacant lot)
3147 S. Grand Ritz Pocket Park (replacing surface parking lot
2800 Minnesota rehab for Carlson Galleries' Saint Louis Lamp Repair
2101 S. Jefferson South Side Early Childhood Center (new construction)
5400 Nottingham rehab for Grapeseed
3159 S. Grand rehab for Bailey's Rooster
Re-opening of rebuilt and improved River des Peres Greenway Trail (Landsdowne trailhead area)
Carondolet Connector of GRG's River des Peres Trail

North City
North Sarah Apartments Phase II - mixed use (103 units + commercial)
1425 Salisbury rehab into Sun Café
Flance Early Learning Center - 1908 O'Fallon (Carr Square/Murphy Park new construction)
26oo N. 14th St. Crown Square occupancy by UrbArts venue
KIPP Academy - 955 Arcade (old Mitchell School in West End)
1600 N. Broadway rehab of vacant warehouse for Bissinger's Chocolates

Expected Completions 2014

Transportation
Partial Completion of Arch Project street work (new on/off ramps, Texas turn-around, replacement of Walnut St. Bridge, removal of Chestnut and Market bridges, completion of south portion of Central Riverfront Trail/LKSullivan, demo of Arch parking garage and closure of Washington)

Downtown
Marquette Building - 304 N. Broadway (10 condos converted from old Y space)
Old Cathedral renovation
Laclede's Landing Plaza & 3rd Street streetscape; cobblestone re-laying
Plaza Square improvements, including new garage (intended to create high occupancy rates)

Central Corridor
Terry Park homes in Gate District (25 single family homes)
245 Union new residential (88 units)
3010 Washington renovation for Salvation Army (58 units at former Harbor Light homeless shelter)
1520 S. Vandeventer rehab for new IT company
Shriner's Hospital - 4440 Clayton Avenue (formerly surface parking)
Cortex Commons (Boyle and Clayton)
3137 Locust rehab for Tempest Distilling
1245 S. Vandeventer for Bruno David Projects

South City
Farmers & Merchant and Lutz buildings rehab into "Southside Station" mixed-use development (39 units) (S. Grand & Gravois)
Rehabs of underutilized Cherokee St. Buildings -- 2648 (Bespoke)
2622 Cherokee container infill for Empire Café
3612 Hartford mixed-use rehab (just off S. Grand)
Subway/mixed-use building - 1151 S. Kingshighway (2nd floor office; demo of existing buildings)
5351 Murdoch rehab for bar/restaurant & retail first floor, apartments above
2212 S. Jefferson - Milque Toast opening

North City
Bremen Homes infill development in Hyde Park (40 homes)
"Blossom House" rehab - 5331 Enright

2014 Announced Projects with post-2014 completion

Downtown
Under Construction
Arcade-Wright - 800 Olive (282 units + Webster U Gateway Campus)
1214 Washington mixed-use (5 units + first floor commercial)
Arch grounds & Central Riverfront Trail
Gen Am Building (700 Market) - renovation for Laclede Gas office relocation
827 Washington - renovation for Marriot Courtyard (old Lennox Hotel)

Planned
Chemical Building (approx. 120 units)
720 Olive (partial conversion to 111 residential units on top floors. consolidation of office to lower floors)
The Alverne Building (1014 Locust) (81 units)
2035 Lucas "Intrada Lofts" (57 units)
1900 Pine (87 units)
615 Washington Ave for National Blues Museum
Laclede's Landing/Arch Third Street Garage with ground floor retail (current surface parking lot)
800 Washington - Renaissance Grand $20 million upgrade/renovation
1011 Olive conversion for Dave Bailey bbq joint and rooftop bar (old Bussone's building)
Expansion of 14th Street Transit Center
Expansion of Eugene Field House & Museum

Central Corridor
Under Construction
City Walk/Whole Foods mixed-use (177 units; 2015 opening)
West Pine Lofts - 4034. W. Pine (206 units) (new construction)
"The Standard" - 3853 Forest Park Ave. (164 unit, 465 bed new residential; August 2015 opening)
Gerhart Block mixed-use renovation (17 units)
Botanical Grove (ongoing UIC rehab and modern infill single family homes)
IKEA - Cortex
WUMC McKinley Research Building (Taylor & McKinley)
WUMC Environmental Health & Safety (Clayton & McKinley)
STLCOP Phase I (Taylor and Parkview Place)
BJC Kingshighway building tear-downs and replacements
Rosati-Kain High School expansion
Commerce Bank @ Manchester & Vandeventer (replace existing)
AT Still Dental (City Hospital complex)
Home2Suites Hilton (Chouteau & Taylor)
Reliance Bank (renovation @ Manchester & Tower Grove)

Planned
2659 Locust (Beaumont Building) 70 unit, market rate rehab (projected fall construction start and late 2015 finish)
Georgian/City Hospital addition of 62 apartments in out building
1917 Rutger conversion of warehouse to 30 residential units & retail
Missouri Theater Building rehab - 634 N. Grand (mixed-use 108 unit residential, commercial and parking garage)
3700-3824 Olive 179 unit student housing project
4100 Lindell (Remington Rand Mid-Modern) renovation into mixed-use (16 units)
4242 Lindell - residential rehab of commercial building (24 units)
4643 Lindell mixed-use tower (217 units)
Silo Lofts - Cortex 200+ units plus ground floor retail
4321-29 Manchester mixed-use modern infill (20 units + ground floor commercial)
6828 Oakland - rehab of vacant MCM commercial building for insurance company
Conversion of vacant CWE church into Cathedral Square Brewery (500 N. Kingshighway)
Loop Trolley and Data Rail
Bike/Ped Improvements to Skinker & Clayton area

South City

Under Construction
5320 Brannon residential conversion of former Hope Lutheran School (24 units)

Planned
Rise/Messiah Lutheran LHTC immigrant rehab project in Fox Park/TGE ( 45 apartment units in 12 properties)
2400 S. 9th residential conversion of Polar Wave Building (43 units)
youth treatment facility at Grand & Gravois
24 single-family Mississippi Bluffs project on S. Broadway
16 single-family Detonty Close project in Shaw
2201 Indiana - Adaptive Rehab of Kinloch Telephone Exchange Building
S. Kingshighway Viaduct
Saint Margaret of Scotland Middle School construction (filling part of surface lot fronting Shaw)
St. Elizabeth's conversion for International Institute (Arsenal St.)

North City
North Sarah Phase III (76 units; unknown if additional commercial space)
Cardinal Ritter former campus redevelopment into Vets housing (5341 Emerson Ave,)
Major expansions in North Riverfront industrial area -- Dial, Green Street, etc.

PostSep 04, 2014#138

I've posted a few updates, including construction starting on the Wash U Environmental Health building and Reliance Bank (in the Grove) and openings of a couple restaurants in formerly neglected storefronts like Lona's Lil Eats and Tick Tock Tavern and Steve's Hot Dogs.

Anything of note I should add?

9,539
Life MemberLife Member
9,539

PostSep 04, 2014#139

Major expansions in North Riverfront industrial area -- Mallinckrodt and Dial companies
that has been put on hold....

8,155
Life MemberLife Member
8,155

PostSep 04, 2014#140

^ too bad. I also remain disappointed in the standstill on new residential project announcements.

But on a better note someone here seemingly in the know mentioned to expect a BPV Phase II announcement sooner than later and Alex Ihnen said he expected news on Midtown Station before long.

edit: I knew if I complained about no residential project announcements we'd get one.... updated for the Polar Wave project in Soulard for 43 apartments.

PostSep 18, 2014#141

Made several additions including adding the planned residential projects in Lafayette Square and Grand Center and moving the Alverne from under construction to planned as just preliminary interior demo is underway and project construction likely won't begin until 2016 (after the owner tackles the larger 720 Olive project).

edit: also moved the Missouri Theater Building from expected 2014 completion (for the commercial portion) to the planned category.... anyone here anything on the status for this? Also haven't heard anything on that Tempest Distillery in Midtown in some time. Anyone?

PostSep 19, 2014#142

Updated to include the truly awesome RISE/Messiah Lutheran rehab project for Bhutanese refugees. I nominate this for Best Project of the Year - Non Downtown Rehab of Historic Building for Residential/University Campus Category.

455
Full MemberFull Member
455

PostSep 24, 2014#143

I think you may be a little premature on the RISE project... it has only requested low-income housing tax credits. Without them getting approved, the project is going nowhere.

1,982
Never Logs OffNever Logs Off
1,982

PostSep 27, 2014#144

roger wyoming II wrote:Also haven't heard anything on that Tempest Distillery in Midtown in some time. Anyone?
I have no idea on the timing, but I do know that Tempest is still in the plans and being worked on, at least on some level. I'd be surprised if it didn't become a reality, but as I said, I have no idea when that will be.

8,155
Life MemberLife Member
8,155

PostSep 27, 2014#145

^ thanks for the update.... I saw their video and it should be a very nice addition to Midtown. I hope it does come to fruition sooner than later!
gregl wrote:I think you may be a little premature on the RISE project... it has only requested low-income housing tax credits. Without them getting approved, the project is going nowhere.
Yeah, sometimes I struggle where to put things... but I believe this is detailed enough to put in the planned projects. (I think I have another list of possible projects of rumor and innuendo floating around somewhere for things like BPV residential tower, etc.) Also, I recall nextstl reporting that it is seeking a smaller tax credit that makes it easier for projects to be awarded. It is a nearly perfect plan so I'll be extremely disappointed if it falls through.

PostOct 03, 2014#146

The Rooster crowed this morning on South Grand. Also, moved Jazz Saint Louis expansion to the completed column!

PostOct 31, 2014#147

Made a few updates including the MCM commercial building on Oakland that will be renovated for the insurance company and the completion of the Garfield School renovation on S. Jefferson for the supportive housing project.

Also, with another month gone by, the turtle race between Loop Trolley and National Blues Museum continues... who will be first to start construction?

PostOct 31, 2014#148

^ I also have to say that if you would have asked me in March what would be the chances of no work getting started by this time on the Chemical, Missouri Theater and OPUS projects plus no announcements yet on Silo Lofts or BPV and Drury towers I'd say they would be about zero, yet here we are.

3,541
Life MemberLife Member
3,541

PostOct 31, 2014#149

^ True, but we have also had quite a few surprises and quick groundbreakings in the last couple months too. I think its all about financing and how good developers are at securing it.

1,320
Veteran MemberVeteran Member
1,320

PostNov 01, 2014#150

Also realize that we're hearing about a lot of projects *long* before they are publicly announced due to this forum and nextStl. Sometimes it just seems like a long time because someone broke the news earlier in the process.