2,151
Life MemberLife Member

Post3:30 PM - Aug 10#951

Oh man - I didn't realize this leg of the brickline was already started - amazing! Thanks dylank

1,041
Expert MemberExpert Member

Post12:42 AM - Aug 11#952

So much potential! Look at the multi family opportunities on the greenway

My only nitpick is more street trees as they do this work


Sent from my iPhone using Tapatalk

330
Full MemberFull Member

Post2:24 PM - Aug 11#953

Partner Projects
  1. 20th Street (St. Louis Ave to City SC) - under construction, moving slow.
  2. Tower Grove Connector - wrapping up Vandeventer segment. Phase 2 construction to follow
Brickline
  1. North Grand (Page to Fairground) is under construction. I expect much of it to be visually complete by Spring of 2027.
  2. Spring (Page to Lindell) breaks ground in the Fall. (South Spring from SLU to Foundry) has been designed, unknown timeline
  3. Market Street (Arch to Tucker) submitted for federal funding. Insight from Downtowners? (Tucker to City SC) before 2030 start.
  4. Spring I-64 Crossing breaks ground in 2027.
  5. Clayton Rd breaks ground before 2030.
  6. Metrolink ROW, connection to Foundry route being re-evaluated
  7. St. Louis Ave. - no date set, in planning.
  8. Forest Park Parkway (Grand to Compton) - unknown timeline (likely part of the Future 64 improvements).
  9. Washington Loop (added segment since Brickline inception) - unknown timeline


2,151
Life MemberLife Member

Post3:25 PM - Aug 11#954

dylank wrote: ↑
2:48 PM - Aug 10
I found this render of this exact spot and delmar2debaliviere2downtown I think you'll get your wish! lol 

3,611
Life MemberLife Member

Post4:11 PM - Aug 11#955

I played baseball at Herbert Hoover Boys and Girls Club as a kid. That was over 30 years ago. I remember the old Carter Carburetor factory. It's exciting seeing that this area will get some investment. Beautiful homes still on the surrounding blocks. A lot of multigenerational black families that own their homes and held on through decades of neglect.

122
Junior MemberJunior Member

Post6:56 PM - Aug 11#956

dylank wrote: ↑
2:48 PM - Aug 10
Where is this?

340
Full MemberFull Member

Post7:00 PM - Aug 11#957

Rick Prieto wrote: ↑
6:56 PM - Aug 11
dylank wrote: ↑
2:48 PM - Aug 10
Where is this?
Looking northbound on Grand just north of St. Louis Avenue. The greenway is on the west side of the Grand.

2,151
Life MemberLife Member

Post7:37 PM - Aug 11#958

stldotage wrote: ↑
7:00 PM - Aug 11
Rick Prieto wrote: ↑
6:56 PM - Aug 11
dylank wrote: ↑
2:48 PM - Aug 10
Where is this?
Looking northbound on Grand just north of St. Louis Avenue. The greenway is on the west side of the Grand.
N. Grand and University Street is right there just passed that historic brick building on the right. 

https://maps.app.goo.gl/odB7uuwnzbUckh8M6

122
Junior MemberJunior Member

Post8:00 PM - Aug 12#959

thanks for sharing the location

2,151
Life MemberLife Member

Post8:33 PM - Aug 12#960

Rick Prieto wrote: ↑
8:00 PM - Aug 12
thanks for sharing the location
I also needed to know as I was confused where it was at first too! :) 

550
Senior MemberSenior Member

Post5:39 AM - Aug 14#961

dylank wrote: ↑
2:24 PM - Aug 11
Partner Projects
  1. 20th Street (St. Louis Ave to City SC) - under construction, moving slow.
  2. Tower Grove Connector - wrapping up Vandeventer segment. Phase 2 construction to follow
Brickline
  1. North Grand (Page to Fairground) is under construction. I expect much of it to be visually complete by Spring of 2027.
  2. Spring (Page to Lindell) breaks ground in the Fall. (South Spring from SLU to Foundry) has been designed, unknown timeline
  3. Market Street (Arch to Tucker) submitted for federal funding. Insight from Downtowners? (Tucker to City SC) before 2030 start.
  4. Spring I-64 Crossing breaks ground in 2027.
  5. Clayton Rd breaks ground before 2030.
  6. Metrolink ROW, connection to Foundry route being re-evaluated
  7. St. Louis Ave. - no date set, in planning.
  8. Forest Park Parkway (Grand to Compton) - unknown timeline (likely part of the Future 64 improvements).
  9. Washington Loop (added segment since Brickline inception) - unknown timeline

Alright hear me out.....lots of back and forth about N/S Metrolink, BRT, blah blah blah. What if we just run self-driving golf cart taxis on the Greenways.... 🤔 😅

127
Junior MemberJunior Member

Post5:24 PM - Aug 14#962

RuskiSTL wrote: ↑
5:39 AM - Aug 14
dylank wrote: ↑
2:24 PM - Aug 11
Partner Projects
  1. 20th Street (St. Louis Ave to City SC) - under construction, moving slow.
  2. Tower Grove Connector - wrapping up Vandeventer segment. Phase 2 construction to follow
Brickline
  1. North Grand (Page to Fairground) is under construction. I expect much of it to be visually complete by Spring of 2027.
  2. Spring (Page to Lindell) breaks ground in the Fall. (South Spring from SLU to Foundry) has been designed, unknown timeline
  3. Market Street (Arch to Tucker) submitted for federal funding. Insight from Downtowners? (Tucker to City SC) before 2030 start.
  4. Spring I-64 Crossing breaks ground in 2027.
  5. Clayton Rd breaks ground before 2030.
  6. Metrolink ROW, connection to Foundry route being re-evaluated
  7. St. Louis Ave. - no date set, in planning.
  8. Forest Park Parkway (Grand to Compton) - unknown timeline (likely part of the Future 64 improvements).
  9. Washington Loop (added segment since Brickline inception) - unknown timeline

Alright hear me out.....lots of back and forth about N/S Metrolink, BRT, blah blah blah. What if we just run self-driving golf cart taxis on the Greenways.... 🤔 😅
YES 💯

2,755
Life MemberLife Member

Post5:02 PM - Aug 15#963

Imagine what this city would look like today if they had finished all of these project 10 years ago

12K
Life MemberLife Member

Post7:09 PM - Aug 15#964

Imagine what it'll look like ten years from now.

2,755
Life MemberLife Member

Post2:37 PM - Aug 16#965

True. I just wish these timescales weren't so long. I feel my life ticking away waiting for this city to improve itself.

3,497
Life MemberLife Member

Post2:59 PM - Aug 16#966

GoHarvOrGoHome wrote: ↑
2:37 PM - Aug 16
True. I just wish these timescales weren't so long. I feel my life ticking away waiting for this city to improve itself.
Should GRG put a new item up for a vote in the 3 counties to double the amount we pay into GRG?  If it lays out exactly how the new money would be spent and by what new timeline, I believe it would pass.  We keep voting to pass region-wide taxes for region-wide improvements.  Arch, GRG, MSD, metro link, Page bridge, etc.  We could write it to only be applied to the counties that approve, so if St. Charles county votes no, so be it.  They get the go-slow current timeline, whereas the county and city could double the timeline speed.

2,755
Life MemberLife Member

Post2:09 PM - Aug 17#967

Why not? No ask, no get. 

It would be great to see Jefferson County eventually added to the GRG system as well

622
Senior MemberSenior Member

Post8:26 AM - Sep 13#968

North Grand at Dodier...
IMG_7546.JPG (5.57MiB)
IMG_7549.JPG (5.61MiB)

North Spring at MLK...
IMG_7554.JPG (7.74MiB)
IMG_7556.JPG (7.97MiB)

6,253
Life MemberLife Member

Post4:02 PM - Sep 13#969

Nice! The whole Grand rebuild has generally been a very positive thing. Glad to see some progress on the north end with the greenway too.

81
New MemberNew Member

Post3:45 PM - Sep 16#970

This is going to be so nice when it's done but it's been so painful in between. The bus stops there are ridiculously dangerous. 

2,979
Life MemberLife Member

Post2:16 PM - Sep 30#971

Brickline Greenway at Cortex MetroLink Station: Complete
Market Street: Compton Ave. to 20th St.: Complete 
Grand & Spring Aves. - Natural Bridge to Page: Construction, Estimated Spring 2027
Spring Avenue between Page & Lindell Blvds.: Awaiting Construction, Estimated Spring 2028
St. Louis Ave.: Planning, No Estimation
MetroLink Corridor: Cortex MetroLink to Forest Park & Spring Aves: This section of greenway is on pause as we re-evaluate route options, then we will resume planning and design.
Midtown I-64 Crossing: Design, Construction estimated 2027
Forest Park to Cortex MetroLink Station: Design, Construction estimated 2029

Painfully slow build-out. Doesn't include a few key sections either. 