Voters do have short-memory spans. For example, I doubt many remember that in 1999, when finally adopted by East-West Gateway and subsequently handed off to Bi-State, the project was only $400 million and scheduled to open in 2004. By 2002, it was a more realistic $550 million and 2005. Of course, that's changed now to $680 million and 2006.
But what many people also forget or fail to have ever learned is that when Metro took charge of the project after discovering the Collaborative's mismanagement and firing them in 2004, the project was looking to be over $700 million and not open until 2007. So indeed, since taking over the project when it wasn't even yet 50% complete, but more than half of even the expanded budget was already gone, Metro has successfully sped up the project and kept the budget in-check.
But what many people also forget or fail to have ever learned is that when Metro took charge of the project after discovering the Collaborative's mismanagement and firing them in 2004, the project was looking to be over $700 million and not open until 2007. So indeed, since taking over the project when it wasn't even yet 50% complete, but more than half of even the expanded budget was already gone, Metro has successfully sped up the project and kept the budget in-check.















