Movement today at the 4101 site. Just a couple bobcats but it's something
MODOT is seeking input on roadway and crosswalk improvements on Manchester in The Grove. Take the survey here:

https://www.surveymonkey.com/r/citySTLs ... 7pMc-jLWe4

Image
Is the Raising Cane’s project dead? I haven’t seen any movement on that one.
^ it's alive; work should start soon.
Permit issued for drilling piers for the Spencer development at 4101 Manchester
The Raising Canes lot has equipment on the site along with some holes drilled through the concrete on there too.